PEMEX GAS Y PETROQUÍMICA BÁSICA (PGPB) / ICA FLUOR DANIEL IN ASSOCIATION WITH LINDE PROCESS PLANNING, INC.

Technical Normative Analysis to determine the legitimacy of the controversy in expedient 90/2012, derived from “Contrato de obra Publica No. GOPL01309P”.


PEMEX GAS Y PETROQUÍMICA BÁSICA (PGPB) / ICA FLUOR DANIEL IN ASSOCIATION WITH LINDE PROCESS PLANNING, INC.
Technical Normative Analysis to determine the legitimacy of the controversy in expedient 90/2012, derived from “Contrato de obra Publica No. GOPL01309P”.


REGIOMONTANA DE CONSTRUCCION Y SERVICIOS, S.A. DE C.V.
Specialized services with respect to the technical-normative revision on the Contract for the foundation and structural work done for the Hematology-Oncological and Research unit of the “Hospital Infantil de Mexico Federico Gomez” in Santa Catarina, Nuevo Leon.


TRADECO INDUSTRIAL S.A. DE C.V
Specialized services with respect to the technical-normative revision to the contract denominated: complementary engineering, procurement, and construction of five 100Mb auxiliary service storage tanks and their integration to the maritime terminal in Tuxpan, Veracruz.


PEMEX REFINACION / DRAGADOS
Technical controversy determined: Consulting services identifying price increase due to time extension on the deadline date for “Obra Publica Mixto No PR-OP-L-025/04P”, as well as consulting request identifying the increase in cost of labor due to modifications made by PEMEX Refinacion to the conditions established in the Tender.


PEMEX REFINACION / ICA FLUOR DANIEL, S. de R.L. de C.V.
Technical controversy determined: Consulting services identifying price increases due to time extension from the deadline date for “Obra Publica Mixto No PR-OP-L-022/04P”, as well as CONSULTING REQUEST IDENTIFYING Consulting request identifying the increase in cost of labor due to the modifications made by PEMEX Refinacion to the conditions established in the Tender.


PEMEX REFINACION / MINATRICO
Technical controversy determined: Consulting services identifying price increases due to time extension on the deadline date for “Obra Publica Mixto No PR-OP-L-002/05P”, as well as Consulting request identifying the increase in cost of labor due to modifications made by PEMEX Refinacion to the conditions established in the Tender.


PEMEX REFINACION / EBRAMEX
Technical controversy determined: Consulting services identifying price increases due to time extension on the deadline date for “Obra Publica Mixto No PR-OP-L-001/05P”, as well as consulting request identifying the increase in cost of labor due to modifications made by PEMEX Refinacion to the conditions established in the Tender.


COCONAL, S.A. de C.V.
Management of and follow up on the contract for the construction of the vehicular bridge between Calle 7 and Av. Pantitlan, in Mexico City.


CERREY
Physical drafted and generated the as-built plans (Quantapoint) of the CFE Plant.


BAKER & MçKENZIE
Participation in the validation for the Award of Responsibility in the international arbitration between PEMEX and The Conproca consortium with relation to the remodeling of the Cadereyta Refinery.


TERCERÍA TECNICA ( CFE – ICA )
Participation in the technical review of a third party, requested by Constructora Internacional de Infraestructura, S.A. de C.V. (CIISA) and Comision Federal de Electricidad (CFE), for the El Cajon hydroelectric project in the complaint petition submitted by the contractor before the Secretary of the Public Function.


MÉXICO CONSTRUCTORA INDUSTRIAL, S.A. DE C.V. (MCI):
Participation in the proposed revision and new presentation of studies for the economic recovery to Alstom, the civil works contract in Central hydroelectric Manuel Moreno Torres, 2nd Stage Units 6-8


MÉXICO CONSTRUCTORA INDUSTRIAL, S.A. DE C.V. (MCI):
Legal and technical advice for the preparation of proposals for tendering: suburban train line 3, construction of macroperas for Pemex and several international tenders.


CHARLES TAYLOR CONSULTING SERVICES, MÉXICO (CTC):
Technical and economic valuation of the repair of damage caused by Hurricane ̈Wilma at the south-west of Mexico (Cancun).

Through inspections, surveys and quantification of damages, costs were valued to compensate for the damage caused, as well as the programming on critical path of all repair work to valuate consequential damages insurance policies.


INSTITUTO NACIONAL  DE LA INFRAESTRUCTURA FÍSICA EDUCATIVA
Elaboration of dictums (3) Regulatory - Technical defects arising from latent defects in the execution of work, for contracts at the Vasconcelos library.


INSTITUTO MEXICANO DEL SEGURO SOCIAL:
Supervision of the construction of the Ambulatory care Medical Unit (IMSS) at San Nicolas de los Garza, N.L.